Schedule


The dates for public scoping meetings and hearings on the Draft Supplemental Environmental Impact Statement (SEIS) for the West Valley Site and the availability of the Draft and Final SEISs are announced in the Federal Register, in the local media, and on this website.


The summary timeline for the Supplemental Environmental Impact Statement (SEIS) for the West Valley Site shows the general schedule for SEIS and related activities. These include more than 90 days for public scoping in the first half of 2018, preparation of the Draft SEIS through 2020, and a 6-month SEIS public comment period in the first half of 2021. The final SEIS will be available in the second quarter of 2022, with the Record of Decision and Findings Statement published at the end of 2022. Phase 2 decommissioning plans and permitting and license applications will also be prepared for completion by the end of 2022 and 2023, respectively.